Wednesday, September 27, 2017

Line Balancing (Designing Product Layout), Cycle time, Precedence diagram, Network analysis, Critical Path Method (CPM)

Line Balancing (Designing Product Layout)

The process of assigning tasks to workstations in such a way that the workstations have approximately equal time requirements
  • The process of deciding how to assign tasks to workstations
  • Minimizes idle time along line & results in a high utilization of labor & equipment

Perfectly balanced line will have a smooth flow of work

Cycle time

The maximum time allowed at each workstation to complete its set of tasks on a unit
  • Establishes the output rate of a line

The primary determinant of line balancing is what the line’s cycle time will be


  • Minimum cycle time is equal to the longest task time(1.0 min.) & the maximum cycle time is equal to the sum of the task times(0.1+0.7+1.0+0.5+0.2+2.5 min.)
  • Minimum cycle time apply if there were five workstations
  • Maximum cycle time apply if all tasks were performed at a single workstation



                               
Assume, line will operate for eight hours per day (480 min.) & cycle time is 1.0 min.
                                                                                                               
Cycle time also can be determined by the desired output rate (suppose 480 units)
                                               

                                                                                                                               
Theoretical minimum number of stations required to provide a specified rate of output


                                                                                                                               
2.5 stations is not feasible, so necessary to round up to three stations (2.5 is minimum)

Precedence diagram (Balancing)

A diagram that shows elemental tasks & their precedence requirements
- A very useful tool in line balancing
- Assign tasks in order of most following tasks
- Assign tasks in order of greatest positional weight (sum of each task’s time)

Assign tasks in order of most number of followers

  1. Begin with task a; it has the most following tasks. Assign it to workstation 1.
  2. Next, tasks b & c each have two following tasks, but only task c will fit in the time remaining at workstation 1, so assign task c to workstation 1.
  3. Task b now has the most followers, but it will not fit at workstation 1, so assign it to workstation 2.
  4. There is no time left at workstation 2, so we move on to workstation 3, assigning task d & then task e to that workstation.

Balancing loss

The percentage of idle time of the line


(Nactual = Actual number of stations)


Parallel workstations (Balancing)



Network (precedence) analysis

Diagram of activities that shows sequential relationships by use of arrows & nodes

  • Graphical display of project activities
  • Estimate of how long the project will take
  • Indication of which activities are the most critical for timely completion
  • Indication of how long any activity can be delayed without delaying the project

Two main methods:-

  1. Critical Path Method (C.P.M.)
  2. Program Evaluation & Review Technique (P.E.R.T.)
  • Activities: Steps that consume resources &/or time.
  • Events: The starting & finishing of activities, designated by nodes in the AOA
  • Activity-on-arrow(AOA): Network diagram convention where arrows designate activities
  • Activity-on-node(AON): Network diagram convention in which nodes designate activities




  • Path: A sequence of activities, leads from the starting node to the finishing node
- AOA diagram, the sequence 1-2-4-5-6 & AON diagram, S-1-2-6-7 is a path
  • Critical path: The longest path; determines expected project duration
  • Critical activities: Activities on the critical path
  • Slack (Float): Allowable slippage for a path; the difference between the length of a path & the length of the critical path

Activity on node format

  • EFT: is the earliest possible time at which an activity can finish
  • EST: is the earliest possible time at which an activity can start
  • LFT: is the latest possible time at which an activity can finish without affecting the completion of project
  • LST: is the latest time by which an activity can start without affecting the completion of project
  • Total float: is the maximum leeway available to an activity (n) such that it will not delay the completion of the project

Total Float(n) = LSTn - ESTn

  • Free Float: is the leeway available to an activity (n) such that it will not affect the float of succeeding activities
Free Float(n) = ESTn+1 - EFTn

 A-O-N Calculations (CPM)

Total & free float Calculations & Critical path


Total & free float Calculations & Critical path




Critical path highlighted in red color (the sequence of activities that takes longest time)
- Any delays of activities on the critical path will delay the entire project
- Only way to make project earlier is to decrease time from critical path operation

Critical Path Method (CPM) assumes

  • The project networks defines a correct sequence of work in terms of technology & workflow
  • Activities are assumed to be independent of one another with clearly start & finish time
  • The activity time estimates are accurate & stable
  • Once an activity is started it continues uninterrupted until it is completed
  • There is infinite resource capacity, at least for the initial (baseline) project analysis

No comments:

Post a Comment